SHOP FLOOR DOCUMENTATION UTORAK 10_12.CATProcess |
|
Part operation : STEZANJE 2 |
GRUBO GLODANJE |
Tool Change.8 Type : Tool Change |
![]() |
Tool : T2 R216.33-16030-AK50P type : End Mill |
GRUBA OBRADA POPRECNOG UTORA 1 Type : Profile Contouring |
![]() |
Tool : T2 R216.33-16030-AK50P type : End Mill |
GRUBA OBRADA POPRECNOG UTORA 2 Type : Profile Contouring |
![]() |
Tool : T2 R216.33-16030-AK50P type : End Mill |
GRUBA OBRADA UZDUZNOG UTORA 1 Type : Profile Contouring |
![]() |
Tool : T2 R216.33-16030-AK50P type : End Mill |
GRUBA OBRADA UZDUZNOG UTORA 2 Type : Profile Contouring |
![]() |
Tool : T2 R216.33-16030-AK50P type : End Mill |
Program cutting time | : | 7' 33'' |
Program total time | : | 15' 25'' |